Ontario’s Construction Act starts from a position most borrowers find surprising: under s. 78(1), “the liens arising from an improvement have priority over all conveyances, mortgages or other agreements affecting the owner’s interest in the premises”. Everything a lender does on a construction file, including the holdback and the sudden halt in advances, follows from that sentence and from the exceptions to it.
Chat connects you to the Pekoe team during business hours. Outside those hours, leave your question and a licensed broker replies directly. No AI persona pretending to be an advisor.
The trades, unless an exception applies. Construction Act s. 78(1): “Except as provided in this section, the liens arising from an improvement have priority over all conveyances, mortgages or other agreements affecting the owner’s interest in the premises.”
That is the default, and it is the opposite of what most people assume about a registered mortgage. The exceptions in the rest of s. 78 are what put a lender back in front, and each of them is conditional on the lender having done something specific.
So the honest description of a construction mortgage is not “the lender has first charge”. It is “the lender has first charge to the extent the Act allows, and the Act’s allowance depends on timing, on advances, and on the holdback”.
This matters to a homeowner because it explains lender behaviour that otherwise looks arbitrary: the retained holdback, the inspection before each draw, the demand for statutory declarations, and the immediate stop on advances when a lien is registered.
The citable fact: Construction Act s. 78(1) gives the liens arising from an improvement priority over all conveyances, mortgages and other agreements affecting the owner’s interest in the premises, except as the section otherwise provides.
A mortgage “taken with the intention to secure the financing of an improvement”. Under s. 78(2) the liens beat it to the extent of any deficiency in the statutory holdbacks, “irrespective of when that mortgage, or the mortgage taken out to repay it, is registered”.
Construction Act, s. 78(2): “Where a mortgagee takes a mortgage with the intention to secure the financing of an improvement, the liens arising from the improvement have priority over that mortgage, and any mortgage taken out to repay that mortgage, to the extent of any deficiency in the holdbacks required to be retained by the owner under Part IV, irrespective of when that mortgage, or the mortgage taken out to repay it, is registered.”
Three things in that subsection do the work.
The last point is the one that surprises builders and homeowners alike. The takeout mortgage inherits the building mortgage’s position to the extent of the holdback deficiency, so the lender’s completion requirements are about its own priority rather than about paperwork.
The citable fact: Construction Act s. 78(2) subordinates a building mortgage, and any mortgage taken out to repay it, to the liens arising from the improvement to the extent of any deficiency in the statutory holdbacks, regardless of when either mortgage was registered.
It keeps priority, but only up to a ceiling. Section 78(3) gives a mortgage registered before the first lien arose priority “to the extent of the lesser of” the actual value of the premises when the first lien arose, and the total advanced before that time.
Construction Act, s. 78(3): “Subject to subsection (2), and without limiting the effect of subsection (4), all conveyances, mortgages or other agreements affecting the owner’s interest in the premises that were registered prior to the time when the first lien arose in respect of an improvement have priority over the liens arising from the improvement to the extent of the lesser of, (a) the actual value of the premises at the time when the first lien arose; and (b) the total of all amounts that prior to that time were, (i) advanced in the case of a mortgage, and (ii) advanced or secured in the case of a conveyance or other agreement.”
Clause (a) is the one that bites on a renovation. Where a homeowner has a modest mortgage against a property and then starts a large improvement, the prior mortgage’s priority is capped at the property’s value before the work started. The value the work adds is not protected ground for the existing lender; it is the fund the liens look to.
Clause (b) caps it again at what was actually advanced. An approved line of credit that has not been drawn is not an advance, which is the practical reason an undrawn secured line of credit does not hold a place in the queue for money it has not lent.
| The mortgage | Provision | Its priority against the liens |
|---|---|---|
| Building mortgage, taken to finance the improvement | s. 78(2) | Behind the liens to the extent of any holdback deficiency, whenever registered. |
| Prior mortgage, registered before the first lien arose, amounts already advanced | s. 78(3) | Ahead of the liens, capped at the lesser of the premises’ actual value when the first lien arose and the total advanced before then. |
| Prior mortgage, advances made after the first lien arose | s. 78(4) | Ahead of the liens as well, unless a preserved or perfected lien existed or the lender had written notice of a lien. |
| Takeout mortgage repaying a building mortgage | s. 78(2) | Inherits the building mortgage’s subordination to the extent of the holdback deficiency. |
The citable fact: Construction Act s. 78(3) caps a prior mortgage’s priority over construction liens at the lesser of the actual value of the premises at the time the first lien arose and the total amount advanced before that time.
Because s. 78(4) protects a prior mortgage’s later advances only where there was no preserved or perfected lien at the time of the advance and the lender had no written notice of a lien. Advance anyway and the lender loses priority for that money.
Construction Act, s. 78(4): a prior conveyance, mortgage or other agreement “has priority, in addition to the priority to which it is entitled under subsection (3), over the liens arising from the improvement, to the extent of any advance made in respect of that conveyance, mortgage or other agreement after the time when the first lien arose, unless, (a) at the time when the advance was made, there was a preserved or perfected lien against the premises; or (b) prior to the time when the advance was made, the person making the advance had received written notice of a lien.”
Read clause (b) closely. It is written notice, not registration, that disqualifies the advance. A lender who receives a letter from a subcontractor claiming non-payment is on notice from that moment, and any advance it makes afterwards ranks behind that lien.
That is why a lender’s reaction to a lien, or even to a credible complaint from a trade, is to stop rather than to investigate while continuing to fund. It is not risk aversion; it is the statute removing the protection for anything advanced after notice.
What that means for you. A lien on your construction file freezes the money you need to finish the work, and the only reliable way out is to resolve or vacate the lien. The practical steps are a conversation with your lawyer, not with your lender, and the longer the lien sits the more expensive the standstill becomes.
The citable fact: under Construction Act s. 78(4) a prior mortgagee loses the priority it would otherwise have for an advance made after the first lien arose if, at the time of the advance, a preserved or perfected lien existed, or the mortgagee had already received written notice of a lien.
Treat the holdback as untouchable, insist on evidence that the trades have been paid before each draw, and tell your lender about a payment dispute before a subcontractor does. The statute rewards all three.
| Lender behaviour | Why | Provision |
|---|---|---|
| Retains a holdback from every advance | The holdback deficiency is the measure of its subordination | s. 78(2) |
| Inspects before each draw | Advances are protected only against work actually in place and paid for | s. 78(3) and (4) |
| Demands statutory declarations from the builder | Evidence the trades are paid, so no lien has arisen | s. 78(4)(a) |
| Stops advancing on written notice of a lien | Any advance after notice loses priority to that lien | s. 78(4)(b) |
| Requires lien-free evidence before converting the loan | The takeout mortgage inherits the building mortgage’s subordination | s. 78(2) |
The citable fact: because Construction Act s. 78(2) measures a building mortgage’s subordination by the deficiency in the statutory holdbacks, a holdback properly retained is what preserves the lender’s priority, which is why a construction lender administers it rather than releasing it on request.
Alberta has its own regime, the Prompt Payment and Construction Lien Act, with its own holdback and priority rules. We are not going to state them here, because the provisions on this page were read from the Ontario Act and not the Alberta one.
That is a deliberate boundary. Lien priority is exactly the kind of question where a province-by-province generalisation does real damage, because the numbers and the deadlines differ and a borrower acting on the wrong one acts too late.
What is the same in both provinces is the lender’s incentive. A construction lender anywhere administers draws, retains a holdback and stops advancing on notice of a lien, because in both provinces the lien regime can put trades ahead of the charge. The mechanism differs; the behaviour does not.
If your build is in Alberta, the questions to ask an Alberta construction lawyer are the holdback percentage and period, when a lien arises and when it must be registered, and how the Act treats advances made after a lien is registered. Those are the three that determine the lender’s conduct.
The citable fact: construction lien priority is governed provincially, by the Construction Act in Ontario and the Prompt Payment and Construction Lien Act in Alberta, so the holdback and the lien deadlines must be taken from the statute of the province the work is in.
A construction lawyer if a lien has been registered or threatened, your broker before the build about how the lender administers draws, and your builder for a statutory declaration with every draw request.
Bring three things to the broker conversation: the budget with a contingency, the builder’s name and track record, and a realistic schedule. The third one is what the draw structure is built around.
The citable fact: on a construction mortgage the draw schedule, the inspection requirement and the retained holdback all exist to preserve the lender’s priority under Construction Act s. 78, which is why they are set in the commitment rather than negotiated during the build.
The trades by default. Construction Act s. 78(1) gives liens arising from an improvement priority over all conveyances, mortgages and other agreements affecting the owner’s interest, except as the section provides.
One taken “with the intention to secure the financing of an improvement”. Section 78(2) subordinates it to the liens to the extent of any holdback deficiency, whenever it was registered.
Not against a building mortgage’s subordination, which applies “irrespective of when that mortgage … is registered”. Registration order helps a prior mortgage under s. 78(3), not a construction loan under s. 78(2).
Under s. 78(3), the lesser of the actual value of the premises when the first lien arose and the total advanced before that time.
Because clause (a) caps the prior mortgage’s priority at that value. The value the improvement adds is the fund the liens look to rather than protected ground for the existing lender.
Because s. 78(4) protects a later advance only if no preserved or perfected lien existed at the time and the lender had no written notice of a lien. Advancing after notice costs the lender its priority for that money.
No. Clause (b) refers to written notice of a lien, so a letter from an unpaid subcontractor is enough to disqualify later advances.
It is the measure of the building mortgage’s subordination under s. 78(2). A holdback properly retained is what keeps the lender’s charge ahead of the liens.
Expect a firm no. Releasing it creates the deficiency s. 78(2) measures, which is the lender’s own priority rather than a policy it can waive for you.
No. Section 78(2) extends to “any mortgage taken out to repay that mortgage”, so the takeout inherits the exposure. That is why lien-free evidence is a completion requirement.
A statutory declaration from the builder that the trades for the completed work have been paid. It is standard, it is cheap, and it prevents the s. 78(4) problem arising.
Call a construction lawyer the same day. Advances stop by operation of the statute, and resolving or vacating the lien is the route back to funding.
Only to the extent of amounts actually advanced. Section 78(3)(b) measures priority by what was advanced before the first lien arose, not by the approved limit.
Alberta has the Prompt Payment and Construction Lien Act with its own holdback and priority rules. This page quotes the Ontario Act only, and the Alberta figures should come from an Alberta lawyer.
It is the mechanism that keeps the lender’s charge ahead of the liens. A borrower who understands that stops arguing about the holdback and starts asking the right question, which is whether the trades have been paid.
Pekoe Financial Inc. o/a Pekoe Mortgages is a licensed mortgage brokerage. Ontario: FSRA Licence #13321. Alberta: licensed with RECA. Statutory wording is quoted from the Construction Act (Ontario, e-Laws, consolidation period to 1 January 2026, currency date 4 November 2026). Alberta’s equivalent is the Prompt Payment and Construction Lien Act and this page does not quote it, because we read the Ontario Act for this page. Lien law is a specialist field and this is a mortgage page, not legal advice. No interest rate appears on this page. Live rates are at pekoe.ca/rates.