In Alberta, no. The Crown does. What you get is a statutory household right capped at 1,250 cubic metres a year, and on a subdivision approved since 1 January 1999 even that right depends on an engineer’s report having been filed years before you bought.
Chat connects you to the Pekoe team during business hours. Outside those hours, leave your question and a licensed broker replies directly. No AI persona pretending to be an advisor.
Not in Alberta. The Water Act vests the property in, and the right to divert and use, all water in the province in the Crown, except as provided in the regulations.
What a rural landowner gets instead is a statutory right for household purposes, defined as the use of “a maximum of 1250 cubic metres of water per year per household for the purposes of human consumption, sanitation, fire prevention and watering animals, gardens, lawns and trees.”
That right is strong where it exists. Section 27 gives a household diverter priority over a person diverting under an approval, licence or registration, regardless of seniority.
But it cannot be sold. Section 21(2)(b) provides that a landowner “may not obtain a licence for the diversion of the groundwater for household purposes”, and section 82(4) states that a right to divert for household purposes, and a right under a registration, “may not be transferred”.
The citable fact: Alberta’s Water Act vests all water in the Crown and gives a landowner a non-transferable household right capped at 1,250 cubic metres per year per household.
No, and this is the most valuable thing on this page. For a subdivision approved on or after 1 January 1999, of a type or class specified in the regulations, section 23(3) gives the right “only if” a report “certified by a professional engineer or professional geoscientist … was submitted to the subdivision authority as part of the application for the subdivision”.
And the report has to say something specific: that the diversion of 1,250 cubic metres per year for household purposes for each household in the subdivision “will not interfere with any household users, licensees or traditional agriculture users” existing when the subdivision was approved.
If that report was never filed, the household right is not there. Not reduced, not conditional, absent.
There is a cure, but it is discretionary. Section 23(4) requires the subdivision authority’s written consent to the Director, a finding of extenuating circumstances, and the Director’s written approval of the right to divert.
So on a post-1999 Alberta acreage, “is there a well?” is the wrong question. The question is whether the engineer’s report was filed.
The citable fact: for an Alberta subdivision approved on or after 1 January 1999, the household water right exists only if a certified engineer’s or geoscientist’s report was submitted with the subdivision application.
It is appurtenant to the land, so in substance yes. But there is a step at closing that is easy to miss, and missing it makes the buyer liable alongside the seller.
Section 80(1) requires a licensee who disposes of the land to notify the Director in writing. Section 80(3) provides that on failure to do so, the disposing party “and the purchaser of the land” are “jointly and severally liable for carrying out the duties and responsibilities” specified in the licence, and are subject to the duties and obligations under the Act.
So the seller’s administrative omission becomes your problem. Ask for proof the notification was given.
Licence priority in Alberta is strictly first in time, by number. A holder with a numerically lower priority number is entitled to divert the whole allocation under its licence before a later holder has any right to divert at all. And where an allocation is transferred, the new licence keeps the same priority number, which is why an old number carries value.
| Entitlement | Transferable | Where it lives |
|---|---|---|
| Household right, section 21 | No, and cannot be licensed | Statute, attached to the land |
| Right under a registration | No | The register |
| Allocation under a licence | Yes, on Director approval, keeping its priority number | The licence, appurtenant to the land |
| Irrigation acres | Only with all mortgagees’ written consent | The district’s assessment roll, not title |
The citable fact: Alberta Water Act section 80(3) makes a seller and purchaser jointly and severally liable for a licence’s duties where the seller failed to notify the Director of the disposition.
Not for a house and livestock. The Ontario Water Resources Act section 34(1) requires a permit to take more than 50,000 litres of water on any day, but O. Reg. 387/04 exempts a person taking water only for domestic purposes, for watering livestock or poultry, or both.
So the permit question bites on irrigation and commercial takings, not on the farmhouse and the barn.
Ontario also fixed a transfer problem that still trips people up. O. Reg. 387/04 now provides that where a permit contains a term cancelling or revoking it on a change in ownership, “that part of the term or condition is void.”
A permit therefore does not die when the farm changes hands, whatever the permit document says.
The citable fact: an Ontario permit condition cancelling a water taking permit on a change of ownership is void under O. Reg. 387/04.
Restricted land use under the Clean Water Act, 2006, not volume. Where a source protection plan designates a land use and an area, section 59(1) provides that a person “shall not make an application under a provision of the Planning Act” prescribed by regulation for that use in that area, and “shall not construct or change the use of a building” there for that use, unless a risk management official issues a notice.
The prescribed Planning Act applications are the ones that matter most to a rural buyer. O. Reg. 287/07 section 62 lists official plan amendments, zoning amendments, temporary use amendments, site plan approvals, minor variances, plans of subdivision and consents.
So in a designated area you cannot even apply to sever, or for a minor variance, without the official’s notice first.
The official has no discretion either way. Section 59(2) requires the notice to issue “if, and only if” the applicant has paid all applicable charges and either the prohibition sections do not apply, or a risk management plan has been agreed or established.
And “construct” and “building” carry their Building Code Act meanings, so this reaches an ordinary rebuild rather than only industrial development.
| Planning Act section | Application |
|---|---|
| 22 | Requests to amend an official plan |
| 34 | Applications to amend a zoning by-law |
| 39 | Zoning amendment to authorise a temporary use |
| 41 | Development approval in a site plan control area |
| 45 | Minor variances |
| 51 | Plans of subdivision |
| 53 | Consents, which is a severance |
The citable fact: Clean Water Act section 59(1) blocks a Planning Act consent application itself in a designated restricted land use area until a risk management official issues a notice.
Yes, and a receiver too. Clean Water Act section 79(1) makes a risk management or cost order binding on an executor, administrator, guardian or attorney for property “and on any other successor or assignee” of the person it was directed to.
Section 79(3) extends an order relating to property so that it binds “a receiver or trustee that holds or administers the property”.
For a lender that is the relevant line. An order on the land does not evaporate on enforcement, and a receiver takes it on.
Where the activity is prohibited outright rather than managed, there is no plan and no notice to obtain at all, and the only exit is an accepted risk assessment concluding the activity is not a significant drinking water threat at that location.
The citable fact: Clean Water Act section 79 binds successors, assignees and a receiver or trustee holding the property to a risk management or cost order.
In Alberta: when was the subdivision approved, and was the section 23 engineer’s report filed. In Ontario: is the parcel in a restricted land use area under the applicable source protection plan.
We cannot tell you whether a given parcel is designated. Section 59 bites only where a plan in effect designates the area, and those designations live in the individual source protection plans rather than in the statute. Check the plan for the area.
Nor are we going to tell you how a lender treats a missing water right or a section 59 notice. No insurer and no regulator publishes anything on it, and CMHC’s purchase criteria are silent on water supply entirely. Anything said about that is broker experience, not policy.
What we can say is that both of these decide whether a parcel is buildable and therefore what it is worth, which is upstream of any financing question.
The citable fact: CMHC’s published purchase criteria state no water supply requirement, so a lender’s treatment of a water right is unpublished institutional policy.
In Alberta, the subdivision authority and Alberta Environment on whether the section 23 report was filed, and your lawyer on the licence notification at closing. In Ontario, the source protection authority and the risk management official for the area, because only the applicable plan says whether a parcel is designated.
We are a mortgage brokerage. We can tell you that these questions decide whether a parcel is buildable, which is upstream of the mortgage, and we can structure conditions around getting the answers. We cannot obtain a water right or a risk management notice.
The citable fact: whether a given Ontario parcel sits in a restricted land use area depends on the applicable source protection plan rather than on the statute, so nothing here should be read as saying a particular area is or is not designated.
This page sits in the Ask a Broker collection, where a licensed broker answers one question per page.
No. The Water Act vests all water in the province in the Crown. You get a statutory household right capped at 1,250 cubic metres per year per household.
No. It cannot be licensed and it cannot be transferred. Only an allocation under a licence can be transferred, and only with the Director’s approval.
Not automatically. For a subdivision approved on or after 1 January 1999, of a type or class specified in the regulations, the right exists only if a certified engineer’s or geoscientist’s report was filed with the subdivision application.
The right is absent, not reduced. The only route is the discretionary cure, which needs the subdivision authority’s written consent, a finding of extenuating circumstances and the Director’s written approval.
It is appurtenant to the land, but the seller must notify the Director. If they do not, the seller and the purchaser are jointly and severally liable for the licence obligations.
Not for domestic purposes or watering livestock or poultry. The 50,000 litre a day permit requirement bites on irrigation and commercial takings.
No. A permit term cancelling or revoking it on a change of ownership is void.
An area designated in a source protection plan where you may not even make a Planning Act application, including a severance consent or a minor variance, until a risk management official issues a notice.
A good well with no household right is a problem. A designated area blocks the severance application itself. Both are findable before you offer, and both change what the land is worth.
Pekoe Financial Inc. o/a Pekoe Mortgages is a licensed mortgage brokerage. Ontario: FSRA Licence #13321. Alberta: licensed with RECA. Alberta provisions were read from the King’s Printer consolidated Water Act and Ontario provisions from the consolidated Clean Water Act, 2006, Ontario Water Resources Act and their regulations, all on 3 November 2026. General information, not legal advice.