In Ontario the answer changed on 1 January 2026. Annual holdback release is now mandatory rather than optional, with a published notice and a 60 to 74 day payment window. Alberta’s progressive release is still optional and still gated.
Chat connects you to the Pekoe team during business hours. Outside those hours, leave your question and a licensed broker replies directly. No AI persona pretending to be an advisor.
10 per cent in both provinces. Ontario’s Construction Act section 22(1) requires an owner to retain a holdback equal to 10 per cent of the price of the services or materials as they are actually supplied, and section 22(3) applies that irrespective of whether the contract provides for partial payments or payment on completion.
That last clause is why you cannot contract out of it. A lump-sum contract with a single payment at the end still carries a statutory holdback.
Alberta’s Prompt Payment and Construction Lien Act section 18(1) sets the same 10 per cent, retained for 60 days.
The citable fact: both Ontario and Alberta require a 10 per cent construction holdback, and Ontario’s applies whether or not the contract provides for progress payments.
Because a holdback shortfall costs the lender its priority. Construction Act section 78(2) gives liens arising from an improvement priority over a construction mortgage to the extent of any deficiency in the required holdbacks, irrespective of when that mortgage is registered.
Read that again, because it is the whole reason draw mortgages work the way they do. Registering first does not protect the lender. Under-retaining the holdback does the damage no matter how early the mortgage went on title.
Alberta resolves the same problem differently and more directly. Section 26 lets a mortgagee authorised by the owner to disburse funds retain the holdback itself, and that retention is deemed to be compliance with section 18.
So in Alberta your lender holding the holdback is expressly contemplated by the statute. In Ontario it is a commercial response to a priority rule.
The citable fact: Construction Act section 78(2) subordinates a construction mortgage to liens to the extent of any holdback deficiency, regardless of registration date.
Annual release became mandatory. Sections 26 to 27.1 were repealed and replaced by S.O. 2024, c. 20, Schedule 4. New section 26(2) provides that following each anniversary of the date the contract was entered into, the owner shall give notice and make payment of accrued holdback.
The mechanics are specific and easy to miss. Section 26(3) requires the owner to publish a notice of annual release of holdback in the prescribed form not later than 14 days after the anniversary, specifying the amount and the intended payment date.
Section 26(4) then sets the payment window: at least 60 days but not later than 74 days after the notice is published. It is a band, not a date.
Section 26(5) requires the contractor to pay subcontractors their accrued holdback not later than 14 days after receiving it.
The citable fact: since 1 January 2026, Construction Act section 26 requires an Ontario owner to publish an annual holdback release notice within 14 days of each contract anniversary and to pay 60 to 74 days after publication.
On one of three named websites. O. Reg. 304/18 section 7 requires the owner to publish a notice of annual release of holdback, Form 6, on a construction trade news website, and section 1 defines that as The Daily Commercial News, Link2Build or Ontario Construction News.
The previous requirement was publication in a construction trade newspaper, and that definition was revoked. Guidance still telling you to place a newspaper advertisement is out of date.
If you are the owner on a multi-year build, that publication is now a recurring obligation with a 14-day deadline attached to a date few people diarise: the anniversary of the contract, not of the start on site.
The citable fact: O. Reg. 304/18 requires the Ontario annual holdback release notice to be published on The Daily Commercial News, Link2Build or Ontario Construction News.
No. Also new on 1 January 2026, Construction Act section 7(1) was amended to include any amount required to be retained by the owner as a holdback within the trust fund held for the benefit of the contractor.
So the holdback sitting in the owner’s hands is trust money, not working capital. Using it for something else is a breach of trust rather than a late payment.
That is a material change for an owner-borrower on a construction file, and it is worth your lawyer’s attention before the money moves.
The citable fact: since 1 January 2026, Construction Act section 7(1) expressly treats an owner’s retained holdback as trust money for the benefit of the contractor.
Up to 90 per cent. Section 24(1) lets a payer make payments on a contract or subcontract up to 90 per cent of the price without jeopardy, unless the payer has received written notice of a lien before making payment.
Written notice of a lien is the trigger that changes everything. Until it arrives, the 90 per cent safe harbour applies; once it does, it does not.
A mortgagee also has its own statutory information right. Section 39(1) lets a person with a lien, a trust beneficiary or a mortgagee require information by written request, to be provided within a reasonable time not exceeding 21 days.
That is a useful tool on a file that has gone quiet, and most borrowers do not know their lender holds it.
| Step | Deadline | Section |
|---|---|---|
| Retain 10 per cent as supplied | Throughout | s. 22(1) |
| Publish the annual release notice | Within 14 days of the contract anniversary | s. 26(3) |
| Owner pays accrued holdback | 60 to 74 days after publication | s. 26(4) |
| Contractor pays subcontractors | Within 14 days of receipt | s. 26(5) |
| Lien expiry | 60 days after the earlier triggering event | s. 31(2)(a) |
| Mortgagee information request | Answered within 21 days | s. 39(1) |
The citable fact: Construction Act section 24(1) permits payment up to 90 per cent of the contract price without jeopardy, until written notice of a lien is received.
On a sliding test. Section 2(1)(b) sets it at 3 per cent of the first $1,000,000 of the contract price, 2 per cent of the next $1,000,000, and 1 per cent of the balance. Section 2(3) deems a contract complete where what remains is not more than the lesser of 1 per cent of the contract price and $5,000.
Those are thresholds in a statute rather than fees, but they drive real money, because they start the lien clock.
Section 31(2)(a) provides that a lien expires at the conclusion of the 60-day period following the earlier of publication of the certificate or declaration and completion, abandonment or termination.
The 60 days people remember is this one. It is the lien expiry period, and since 1 January 2026 it is no longer the holdback release trigger on a multi-year job.
The citable fact: Ontario’s substantial performance test is 3 per cent of the first $1,000,000, 2 per cent of the next $1,000,000 and 1 per cent of the balance.
Alberta’s progressive release is still optional and gated, which is the opposite of Ontario’s new rule. Section 24.1(2) applies only where the contract provides for annual or phased payment of accrued amounts, the contract price exceeds a prescribed amount, and there are no liens filed as at the payment date.
We are not stating that prescribed amount. It sits in the Alberta Prompt Payment and Adjudication Regulation, which we could not read on this machine, and a figure we cannot source is worse than none. Ask an Alberta construction lawyer.
Alberta also varies the holdback period by trade, which is rarely mentioned. Section 18(1.1) sets 90 days for work on an oil or gas well or well site, and section 18(1.2) sets 90 days for improvements primarily related to the furnishing of concrete.
So a concrete subtrade on an Alberta project sits under a 90 day holdback while the rest of the job sits under 60.
| Feature | Ontario | Alberta |
|---|---|---|
| Holdback percentage | 10 per cent | 10 per cent |
| Standard retention period | Tied to lien expiry, 60 days | 60 days |
| Longer period for some work | None | 90 days for oil and gas well work and concrete |
| Annual or phased release | Mandatory since 1 January 2026 | Optional, and conditional |
| Mortgagee may hold the holdback | Not addressed in the Act | Yes, deemed compliance, s. 26 |
| Holdback is trust money | Yes, s. 7(1) since 1 January 2026 | Not stated in these provisions |
The citable fact: Alberta extends the construction holdback period to 90 days for oil and gas well work and for improvements primarily related to the furnishing of concrete.
Match the draw schedule to the statutory deadlines, and diarise the contract anniversary. The holdback is not the lender being difficult. It is a priority rule the lender cannot waive without losing its security position.
Ask three questions before you sign: who retains the holdback, when the annual release notice gets published and by whom, and what evidence the lender wants before each advance.
Draw frequency, interest reserve sizing, title searches before each advance and whether a quantity surveyor is engaged are all contractual rather than statutory. No statute settles them, so they are negotiable and should be negotiated.
The citable fact: draw frequency, interest reserve and advance conditions are contractual rather than statutory, so they are negotiable, while the holdback itself is not.
No. This page is general information about Ontario’s Construction Act as consolidated to 1 January 2026, and about Alberta’s Prompt Payment and Construction Lien Act. Holdback, lien and prompt payment deadlines are unforgiving, and they belong with a construction lawyer in the province where the work is being done.
We are a mortgage brokerage. We can tell you whether a draw schedule matches the statutory deadlines and what each advance will require. We do not publish your release notices, we do not calculate substantial performance, and we cannot advise on a lien.
The citable fact: the Alberta provisions described here are given in paraphrase rather than quotation, because the authoritative text is a King’s Printer PDF that should be read directly before anyone relies on its wording.
This page sits in the Ask a Broker collection, where a licensed broker answers one question per page.
Ten per cent in both Ontario and Alberta. In Ontario, Construction Act section 22(3) applies it whether or not the contract provides for progress payments, so a lump-sum contract still carries one.
Because section 78(2) gives liens priority over a construction mortgage to the extent of any holdback deficiency, regardless of when the mortgage was registered. A shortfall costs the lender its priority.
Annual holdback release became mandatory. Sections 26 to 27.1 were repealed and replaced, and the new section 26(2) says the owner shall give notice and pay accrued holdback after each contract anniversary.
At least 60 days but not later than 74 days after the annual release notice is published, under section 26(4). It is a window, not a single date.
On The Daily Commercial News, Link2Build or Ontario Construction News, under O. Reg. 304/18. The old requirement to publish in a construction trade newspaper was revoked.
No. Since 1 January 2026, section 7(1) expressly includes an owner’s retained holdback in the statutory trust for the benefit of the contractor.
Up to 90 per cent of the price, under section 24(1), unless the payer has received written notice of a lien before making payment.
No. Alberta’s progressive release is still optional and conditional, it extends the holdback to 90 days for oil and gas well work and for concrete, and section 26 expressly allows a mortgagee to hold the holdback.
Send us the commitment and the construction contract and we will show you where the draw schedule and the holdback deadlines disagree, before the first advance rather than after.
Pekoe Financial Inc. o/a Pekoe Mortgages is a licensed mortgage brokerage. Ontario: FSRA Licence #13321. Alberta: licensed with RECA. This page summarises Ontario’s Construction Act and O. Reg. 304/18 as consolidated to 1 January 2026, and describes Alberta’s Prompt Payment and Construction Lien Act in paraphrase rather than quotation. It is general information, not legal advice. Construction lien law is unforgiving on timing. Get a construction lawyer in the right province before relying on any deadline here.